Bury's motorists will have 13 road closures to avoid on the National Highways network this week.
Eight of them are expected to cause moderate delays with drivers facing hold-ups of between 10 and 30 minutes.
The latest expected works list, with notes from National Highways, shows that 14 closures are due to start over the next two weeks:
• M60, from 9pm March 5 to 6am March 6, moderate delays of 10 to 30 minutes: M66 southbound, junction three exit slip road closure due to works for TfGM.
• M66, from 8pm March 6 to 5am March 8, slight delays of under 10 minutes: M66 northbound, junction 4 to junction 3 - lane closure for barriers which will be permanent on behalf of National Highways.
• M60, from 8pm March 7 to 5am March 8, slight delays of under 10 minutes: M60 clockwise junction 18 to junction 19 - lane closure for barriers which will be permanent on behalf of National Highways.
• M60, from 9pm March 7 to 6am March 23, moderate delays of 10-30 minutes: M60 both directions junction 18 to junction 19 - lane closures and carriageway closure for white lining/road markings on behalf of National Highways.
• M60, from 9pm March 9 to 5am March 11, moderate delays of 10-30 minutes: M60 both directions, junction 18 to junction 19 - lane closure and carriageway closure for barrier repairs.
• M60, from 9pm March 10 to 5am March 11, slight delays of under 10 minutes: M60 both directions, junction 16 to junction 18 - lane closure for barriers which will be permanent on behalf of National Highways.
• M60, from 8pm March 12 to 5am March 13, slight delays of under 10 minutes: M60 both directions junction 16 to junction 17 - lane closure for communications.
• M60, from 8pm March 13 to 6am March 14, moderate delays of 10-30 minutes: M60 clockwise, junction 18 to junction 19 - carriageway closure for sign erection on behalf of National Highways.
• M60, from 8pm March 13 to 6am March 14, moderate delays of 10-30 minutes: M60 clockwise junction 16 to junction 17 - carriageway closure for sign erection.
• M60, from 11.59pm March 14 to 6am March 15, moderate delays of 10-30 minutes: M62 eastbound, junction 17 to junction 19 - carriageway closure for horticulture.
• M62, from 8pm March 15 to 5am March 16, slight delays of under 10 minutes: M60 anti-clockwise junction 18 - lane closure for barriers which will be permanent on behalf of National Highways.
• M66, from 9pm March 16 to 6am March 17, moderate delays of 10-30 minutes: M66 both directions junction 0 to junction 2 - carriageway closure for structure - maintenance.
• M60, from 9pm March 16 to 5am March 18, moderate delays of 10-30 minutes: M60 anti-clockwise, junction 18 to junction 15 - lane closure for barriers which will be permanent.
National Highways is responsible for maintaining motorways and major A-roads, so closures of smaller roads will not be included in their schedule.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here